Production Process - KD Process
Preparation
- All the sawn timber with the same thickness (with 10% tolerance) have to be stack properly into pallets
- Each pallet of sawn timber will be load to chamber after air dry using forklift truck
Processing
- Water spraying will treat all the timber in the chamber become the same humidity
- Temperature and humidity adjustment process has programmed to reach the moisture content target (normally from 8 to 10%)
Finishing
- Temperature conditiong is a process to avoid crack, split, moist etc
- Discharge the sawn timber from the chamber
- Unstacked the sawn timber and deliver to the processing department
The whole process in this department will take about 30 days
[Previous Process - Transportation] |
[Next Process - Wood Working Process]
|
|